RTLS – Implementation to start August 7, 2012

Posted by Russ Arnett in Projects and Risks.
add a comment

We did just have a internal stratagey meeting to discuss the needs and basic requirements as the support team.  Meetings have been idenhat with the vendor who will be leading us through this process over the next two weeks before the offical kick-off with the business users.

Issues that are lurking just on this short meeting:

– Server size, the presented requirements are larger than the local tech person belives are required

– Installation of cable and RTLS equipment – the vendor wants to use a local vendor that the customer uses to install all cable and equipment, the local staff I know will be against this.

So this will become a project with several low level – emotional – types of issues.  So we will see who the grown ups are

 